Sec. 10. Limited applicability.
44 words·~1 min read·
/il/chapter-505/act-17/10A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Sec. 10. Limited applicability. This Act shall not apply to a production contract under the provisions of which the commodity is to be delivered by the producer to the contractor or the contractor's designee within 30 days after the date of the production agreement.