(Section scheduled to be repealed on January 1, 2027)
76 words·~1 min read·
/il/chapter-30/act-538/1-10A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(Section scheduled to be repealed on January 1, 2027)
Sec. 1-55. Transition to design-bid-build. At the completion of design development, the progressive design-build entity must provide a firm fixed price. The State construction agency reserves the right to transition the project to the design-bid-build method if the fixed price exceeds the project budget, the progressive design-build entity's proposed schedule is unreasonable, or if transitioning to the design-bid-build method is in the best interests of the State.