Sec. 3.130. Facility, system, and equipment violations; Plans of Correction.
231 words·~1 min read·
/il/chapter-210/act-50/3-130A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Sec. 3.130. Facility, system, and equipment violations; Plans of Correction. Except for emergency suspension orders, or actions initiated pursuant to Sections 3.117(a), 3.117(b), and 3.90(b)(10) of this Act, prior to initiating an action in response to a facility, system, or equipment violation, the Department shall:
(a)Issue a Notice of Violation which specifies the Department's allegations of
noncompliance and requests a plan of correction to be submitted within 10 days after receipt of the Notice of Violation;
(b)Review and approve or reject the plan of correction. If the Department rejects the
plan of correction, it shall send notice of the rejection and the reason for the rejection. The party shall have 10 days after receipt of the notice of rejection in which to submit a modified plan;
(c)Impose a plan of correction if a modified plan is not submitted in a timely manner
or if the modified plan is rejected by the Department;
(d)Issue a Notice of Intent to fine, suspend, revoke, nonrenew or deny if the party has
failed to comply with the imposed plan of correction, and provide the party with an opportunity to request an administrative hearing. The Notice of Intent shall be effected by certified mail or by personal service, shall set forth the particular reasons for the proposed action, and shall provide the party with 15 days in which to request a hearing.