476A.9 Advance site preparation.
77 words·~1 min read·
/ia/chapter-476a-electric-power-generation-and-transmission/476a-9·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Subsequent to the hearing held pursuant to section 476A.5 and in the event of extensive delay in the issuance of a certificate, the commission may permit an applicant having an application docketed for hearing to begin work to prepare the site for construction of the facility. Any activities conducted pursuant to this section shall have no probative value in the commission’s decision concerning the actual issuance of a certificate.
[C77, 79, 81, §476A.9]
Referred to in §476A.2