Tap any paragraph to write a margin note. Your notes collect in the Desk below the text and file under cases with @. The side-by-side margin rail opens on a larger screen.

Code · Iowa · Chapter 476A — Electric Power Generation And Transmission

476A.9 Advance site preparation.

77 words·~1 min read·/ia/chapter-476a-electric-power-generation-and-transmission/476a-9·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

Subsequent to the hearing held pursuant to section 476A.5 and in the event of extensive delay in the issuance of a certificate, the commission may permit an applicant having an application docketed for hearing to begin work to prepare the site for construction of the facility. Any activities conducted pursuant to this section shall have no probative value in the commission’s decision concerning the actual issuance of a certificate.
[C77, 79, 81, §476A.9]
Referred to in §476A.2
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.