476A.3 Application submitted — review.
82 words·~1 min read·
/ia/chapter-476a-electric-power-generation-and-transmission/476a-3·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
An application for a certificate or an amendment to a certificate shall be submitted to the commission on such forms as the commission may prescribe. Copies of the application shall be forwarded to regulatory agencies. Regulatory agencies receiving a copy of the application shall conduct a preliminary review of the contents and shall evaluate the application for completeness and compliance with the regulatory agency’s permit and licensing requirements within a reasonable amount of time.
[C77, 79, 81, §476A.3]
Referred to in §476.53