Sec. 16a-38f. Agency decision outlines.
77 words·~1 min read·
/ct/title-16a/chapter-298-energy-utilization-and-conservation/16a-38f·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Any agency having authority to make any agency decision with respect to an energy-saving capital project which has been designated as a priority energy project shall provide the commissioner with a decision outline within thirty days after such designation. Such decision outline shall include a statement of necessary actions to be taken by such agency, a schedule for completing such actions and a list of actions required of the agency of the state which requested the designation.