Sec. 16-50cc. Reconfiguration or burial of electric transmission facility.
75 words·~1 min read·
/ct/title-16/chapter-277a-public-utility-environmental-standards-act/16-50cc·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
If legislation adopted on or after January 1, 2004, results in the reconfiguration or burial of a proposed facility described in subdivision
(1)of subsection
(a)of section 16-50i , all prudent costs incurred by an electric distribution company, as defined in section 16-1 , associated with the reconfiguration or burial shall be deemed to be reasonable pursuant to sections 16-19 and 16-19e and shall be recovered by the electric distribution company in its rates.