Tap any paragraph to write a margin note. Your notes collect in the Desk below the text and file under cases with @. The side-by-side margin rail opens on a larger screen.

Code · California · Public Resources Code

§ 21189.82

888 words·~4 min read·/ca/public-resources-code/21189-82

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(A)The Governor may certify a project as an energy infrastructure project for purposes of this chapter if the project meets the requirements of subdivision
(d)of Section 21189.81.
(B)In addition to subparagraph (A), if the applicant is not the lead agency, the Governor shall ensure all of the following:
(i)The applicant agrees to pay the costs of the trial court and the court of appeal in hearing and deciding any case challenging a lead agency’s action on a certified project under this division, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner as provided in the rule of court adopted by the Judicial Council under Section 21189.85.
(ii)The applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with the review and consideration of the project under this division, in a form and manner specified by the lead agency for the project.
(iii)For a project for which environmental review has commenced, the applicant demonstrates that the record of proceedings is being prepared in accordance with Section 21189.86.
(A)The Governor may certify a project as a semiconductor or microelectronic project for purposes of this chapter if the project meets the requirements of subdivision
(f)of Section 21189.81.
(B)In addition to subparagraph (A), if the applicant is not the lead agency, the Governor shall ensure all of the following:
(i)The applicant agrees to pay the costs of the trial court and the court of appeal in hearing and deciding any case challenging a lead agency’s action on a certified project under this division, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner as provided in the rule of court adopted by the Judicial Council under Section 21189.85.
(ii)The applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with the review and consideration of the project under this division, in a form and manner specified by the lead agency for the project.
(iii)For a project for which environmental review has commenced, the applicant demonstrates that the record of proceedings is being prepared in accordance with Section 21189.86.
(3)The Governor may certify up to 20 transportation-related projects for purposes of this chapter, including up to 10 state projects proposed by the Department of Transportation and up to 10 local or regional projects, that meet the requirements of subdivision
(g)of Section 21189.81.
(A)The Governor may certify a project as a water-related project for purposes of this chapter if the project meets the requirements of subdivision
(h)of Section 21189.81.
(B)In addition to subparagraph (A), the Governor shall ensure all of the following:
(i)The applicant agrees to pay the costs of the trial court and the court of appeal in hearing and deciding any case challenging a lead agency’s action on a certified project under this division, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner as provided in the rule of court adopted by the Judicial Council under Section 21189.85.
(ii)The applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with the review and consideration of the project under this division, in a form and manner specified by the lead agency for the project.
(iii)For a project for which environmental review has commenced, the applicant demonstrates that the record of proceedings is being prepared in accordance with Section 21189.86.
(C)In addition to subparagraphs
(A)and (B), the Governor may certify a project as a water-related project for purposes of this chapter only if the Governor finds that greenhouse gas emissions resulting from the project will be mitigated to the extent feasible.
(b)The Office of Planning and Research may consult with other state agencies on and may issue guidelines regarding applications for and the certification of projects under this chapter. Any guidelines issued under this subdivision are not subject to the rulemaking provisions of the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code).
(c)An applicant for certification of an infrastructure project under this chapter shall do all of the following:
(1)Avoid or minimize significant environmental impacts in any disadvantaged community.
(2)If measures are required pursuant to this division to mitigate significant environmental impacts in a disadvantaged community, mitigate those impacts consistent with this division, including Section 21002. Mitigation measures required under this subdivision shall be undertaken in, and directly benefit, the affected community.
(3)Enter into a binding and enforceable agreement to comply with this subdivision in its application to the Governor and to the lead agency prior to the agency’s certification of the environmental impact report for the project.
(d)The Office of Planning and Research shall make evidence and materials submitted for the certification of a project available to the public on its internet website at least 15 days before the certification of the project.
(e)The Governor’s decision to certify a project shall not be subject to judicial review.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.