Code · California · Public Contract Code

§ 20119.2

450 words·~2 min read·/ca/public-contract-code/20119-2

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)The governing board, for projects over one million dollars ($1,000,000), may use the best value procurement method in accordance with this article.
(b)The bidder may be selected on the basis of the best value to the governing board of the school district. In order to implement this method of selection, the governing board of the school district shall adopt and publish procedures and required guidelines for evaluating the qualifications of the bidders that ensure the best value selections by the school district are conducted in a fair and impartial manner. These procedures and guidelines shall conform to this article and shall be mandatory for the school district when using best value selection.
(c)If the governing board of the school district deems it to be for the best interest of the school district, the governing board of the school district, on the refusal or failure of the selected bidder for a project to execute a tendered contract, may award it to the bidder with the second lowest best value score. If the second bidder fails or refuses to execute the contract, the governing board of the school district may likewise award it to the bidder with the third lowest best value score.
(d)The governing board of the school district shall let any contract for a project pursuant to this article to the selected bidder that represents the best value or else reject all bids.
(1)If the school district elects to award a project pursuant to this section, retention proceeds withheld by the district from the selected best value contractor shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation of bids.
(2)In a contract between the selected best value contractor and a subcontractor, and in a contract between a subcontractor and any subcontractor thereunder, the percentage of the retention proceeds withheld shall not exceed the percentage specified in the contract between the district and the selected best value contractor. If the selected best value contractor provides written notice to a subcontractor that, prior to or at the time the bid is requested, a bond may be required and the subcontractor subsequently is unable or refuses to furnish a bond to the selected best value contractor, then the selected best value contractor may withhold retention proceeds in excess of the percentage specified in the contract between the district and the selected best value contractor from any payment made by the selected best value contractor to the subcontractor.
(f)All subcontractors bidding on contracts pursuant to this chapter shall be afforded the protection contained in Chapter 4 (commencing with Section 4100) of Part 1.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.