(a)An application for a project grant shall be reviewed by the administering district immediately upon receipt. If the administering district determines that an application is incomplete, the applicant shall be notified within 30 working days with an explanation of what is missing from the application. The date and time of receipt of each application determined to be complete shall be recorded and the completed application shall be evaluated with respect to the appropriate project selection criteria. A district shall make every effort to process an application and grant an award rapidly and to coordinate project approval with any purchase or installation timing constraint on an applicant. Notwithstanding any other provision of this chapter, the administering district may determine that an application is not in good faith, not credible, or not in compliance with this chapter and its objectives.
(b)A participating district may request assistance from the state board on an as-needed basis to clarify project evaluation protocols or to obtain information necessary to properly evaluate an application.
(c)An application for a grant for an infrastructure project shall be reviewed by the commission immediately upon receipt. If the commission determines that an application is incomplete, the applicant shall be notified within five working days with an explanation of what is missing from the application. The date and time of receipt of each application determined to be complete shall be recorded and the completed application shall be evaluated with respect to the appropriate project selection criteria. A complete grant application fulfilling the project selection criteria shall be approved as soon as practicable, but not later than 60 working days after receipt. Notwithstanding any other provision of this chapter, the commission may determine that an application is not in good faith, not credible, or not in compliance with this chapter and its objectives. The commission shall expedite the processing of an application and shall grant an award as rapidly as possible.
(d)Funds shall be awarded in conjunction with the execution of a contract that obligates the state board or a participating district to make the grant and obligates the grantee to take the actions described in the grant application. A contract shall incorporate the recapturing provisions contained in subdivision
(c)of Section 44291.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.