§ 14072.4
102 words·~1 min read·
/ca/government-code/14072-4A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
As part of the business plan required by subdivision
(b)of Section 14070.4 that is due by April 1, 2024, and each year thereafter, the LOSSAN Rail Corridor Agency shall do all of the following:
(a)Include a description of the effects of climate change, including sea level rise and weather-related events, on the corridor, including how to adapt to its impacts.
(b)Identify projects planned, as part of the capital improvement programs, to increase climate resiliency on the corridor.
(c)Discuss possible funding options for the projects identified pursuant to subdivision (b), including, but not limited to, federal and state funding.