A claimant other than a direct contractor may not enforce a lien unless the claimant records a claim of lien within the following times:
(a)After the claimant ceases to provide work.
(b)Before the earlier of the following times:
(1)Ninety days after completion of the work of improvement.
(2)Thirty days after the owner records a notice of completion or cessation.