Sec. 3128. Integrated schedule for future-years nuclear security program
140 words·~1 min read·
/bill/118/hr/2670/enr/section-3128·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
The Administrator for Nuclear Security shall— develop and maintain a high-level milestone schedule document for all covered construction projects that includes production infrastructure modernization schedules with weapons modernization programs; and for each covered construction project included in the high-level milestone schedule document under paragraph (1), include in such document an identification and explanation of the status of any associated integrated master schedule. The milestone schedule document required under subsection
(a)shall be included in the future-years nuclear security program for fiscal year 2025 and each subsequent fiscal year. In this section, the term covered construction project means— a construction project that is subject to Department of Energy Order 413.3B, or a successor order; or a program designated as Enhanced Management A or B under the Program Execution Instruction of the Office of Defense Programs of the National Nuclear Security Administration.