Sec. 203. New nuclear energy project application reviews
124 words·~1 min read·
/bill/116/s/4897/rs/section-203A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
In reviewing an application for an early site permit, construction permit, operating license, or combined construction permit and operating license for a production, utilization, or fuel facility located at the site of a licensed production, utilization, or fuel facility, the Commission, to the maximum extent practicable, shall use information that was part of the licensing basis of the licensed production, utilization, or fuel facility. Nothing in this section exempts the Commission from any requirement to be fully compliant with section 102(2)(C) of the National Environmental Policy Act of 1969 ( 42 U.S.C. 4332(2)(C) ).
Nothing in this section precludes the Commission from using new information or new scientific or technical analyses that are applicable to the review of an application described in subsection (a).
Connectionstraces to 1
Citation graph
cites case law
Sec. 203
New nuclear energy project application reviews
Cites 1Cited by 0 across 0 sources