Sec. 110. Notifications of permit to drill

1,363 words·~6 min read·/bill/116/hr/4294/ih/section-110

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

The Mineral Leasing Act ( 30 U.S.C. 181 et seq.) is amended by inserting after section 45, as added by section 104, the following: Not later than 1 year after the date of the enactment of this section, the Secretary shall establish procedures by which an operator may conduct drilling and production activities on available Federal land and non-Federal land that is located in a State to which the Secretary has not delegated exclusive authority under section 44(a)(1) after sending to the Secretary a notification of permit to drill under this section in lieu of obtaining an Application for Permit to Drill.
To be considered a complete notification of permit to drill under this section, an operator shall include in the notification of permit to drill submitted under this section— a notification of permit to drill form; a surface use plan of operations; a drilling plan; a well plat certified by a registered surveyor; an operator certification; evidence of bond coverage; and a notification of permit to drill fee in an amount to be determined by the Secretary. Except as otherwise provided in this subsection, the Secretary may not object to a notification of permit to drill under this section if the notification— demonstrates that the drilling operations described in the notification of permit to drill will be located in— a developed field, where there are existing oil and gas wells within a 5-mile radius and for which an approved land use plan or environmental review was prepared within the last 10 years under the National Environmental Policy Act of 1969 ( 42 U.S.C. 4321 et seq.) that analyzed such drilling operations as a reasonably foreseeable activity; a location or well pad site at which drilling has occurred within 10 years before the date of spudding the well and the proposed operations do not increase the surface disturbance on the location or well pad site; an area consisting of individual surface disturbances of less than 10 acres and the total surface disturbance on the lease is not greater than 150 acres and for which an approved land use plan or environmental review was prepared within the last 10 years under the National Environmental Policy Act of 1969 ( 42 U.S.C. 4321 et seq.) that analyzed such drilling operations as a reasonably foreseeable activity; an area consisting of Federal mineral interests that is located within the boundaries of a communitization agreement or unit agreement which contains minerals leased by a State or private mineral owner for which a drilling permit has been approved by a State regulatory agency; or an area in which a categorical exclusion under the National Environmental Policy Act of 1969 ( 42 U.S.C. 4321 et seq.) applies for oil and gas drilling or re-entry activities; or includes— an environmental review that concludes that actions described in the notification of permit to drill pose no significant effects on the human environment or threatened or endangered species; and an archeological review that concludes that actions described in the notification of permit to drill pose no significant effects on cultural or historic properties or resources.
Notwithstanding paragraph (1), the Secretary shall object to a notification of permit to drill if the activity described in such notification of permit to drill is likely to jeopardize the continued existence of a species that is a threatened species or endangered species under the Endangered Species Act of 1973 ( 16 U.S.C. 1531 et seq.) or result in the destruction or adverse modification of critical habitat of such species. The Secretary may withdraw an objection under subparagraph
(A)if the operator consults with the Secretary on such objection and places conditions on the notification of permit to drill sufficient to comply with the Endangered Species Act of 1973 ( 16 U.S.C. 1531 et seq.). Notwithstanding paragraph (1), the Secretary shall object to a notification of permit to drill if the activity described in such notification of permit to drill is likely to affect properties listed, or eligible for listing, in the National Register of Historic Places under section 306108 of title 54, United States Code (commonly known as the National Historic Preservation Act of 1966). The Secretary may withdraw an objection under subparagraph
(A)if the operator consults with the Secretary on such objection and places conditions on the notification of permit to drill sufficient to comply with section 306108 of title 54, United States Code (commonly known as the National Historic Preservation Act of 1966). Not later than 15 days after receipt of a notification of permit to drill, or a revised notification of permit to drill, from an operator under this section, the Secretary shall notify the operator in writing if the notification of permit to drill is not complete. The Secretary shall notify an operator of any objections to the notification of permit to drill not later than 45 days after receipt of a complete notification of permit to drill from an operator under this section. If the Secretary has not notified an operator under either paragraph
(1)or paragraph
(2)within 45 days after receipt of a notification of permit to drill from the operator under this section, the operator may, without further action from the Secretary, conduct the drilling and production activities for which the notification of permit to drill was submitted. If the Secretary notifies an operator under paragraph
(1)of an incomplete notification or paragraph
(2)of an objection, the Secretary shall allow the operator to address such incomplete notification or objection and revise and resubmit the notification of permit to drill. If the Secretary notifies an operator under paragraph
(2)of an objection, the Secretary shall allow the operator to resubmit such information in the form of an Application for Permit to Drill. The Secretary may not charge an operator under this section a fee for submitting a notification of permit to drill greater than the fee the Secretary charges an applicant for an Application for Permit to Drill. An environmental review or archeological review described in subsection (c)(1)(B) may be completed by a third-party contractor approved by the Secretary or pursuant to a memorandum of understanding between the operator and the Secretary. The Secretary shall issue a field work authorization to a third-party contractor for the purposes of paragraph
(1)within a reasonable time. The Secretary shall allow a third-party contractor to submit a request to the State Historic Preservation Office on behalf of the Secretary. The Secretary may not require an operator that has submitted a notification of permit to drill for which the Secretary did not object to obtain a surface use permit for an action included in the notification of permit to drill. The Secretary may not require an operator that has submitted a notification of permit to drill for which the Secretary did not object to submit to a site inspection before commencement of the activities described in the notification of permit to drill. The Secretary may conduct inspections of and evaluate activities described in a notification of permit to drill for purposes of bringing an enforcement action. The Secretary may suspend enforcement proceedings if the operator modifies its activities to comply with the notification of permit to drill or obtains an Application for Permit to Drill for such activities. The decision by the Secretary to take no action under subsection (c)(1)(B)(2) shall not constitute a major Federal action under section 102(2)(C) of the National Environmental Policy Act of 1969 ( 42 U.S.C. 4332(2)(C) ). The development of any regulation pursuant to this section shall constitute a major Federal action under section 102(2)(C) of the National Environmental Policy Act of 1969 ( 42 U.S.C. 4332(2)(C) ). In this section: The terms Application for Permit to Drill , applications for Permit to Drill , available Federal land , and drilling plan have the meaning given those terms in section 44. The term surface use plan of operation means a plan containing— the road and drill pad location; details of pad construction; methods for containment and disposal of waste material; plans for reclamation of the surface; any other information specified in applicable orders or notices; and any other pertinent data as the Secretary may require. .
Connectionstraces to 4
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.