Sec. 630.
90 words·~1 min read·
/bill/116/hr/21/eh/section-630A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
None of the funds appropriated or other-wise made available by this Act may be used to pay award or incentive fees for contractors whose performance has been judged to be below satisfactory, behind schedule, over budget, or has failed to meet the basic requirements of a contract, unless the Agency determines that any such deviations are due to unforeseeable events, government-driven scope changes, or are not significant within the overall scope of the project and/or program and unless such awards or incentive fees are consistent with 16.401(e)(2) of the FAR.