Sec. 304.
56 words·~1 min read·
/bill/116/hr/133/eah/section-304A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
None of the funds made available in this title may be used to approve critical decision-2 or critical decision-3 under Department of Energy Order 413.3B, or any successive departmental guidance, for construction projects where the total project cost exceeds $100,000,000, until a separate independent cost estimate has been developed for the project for that critical decision.