Sec. 1176. Preconstruction engineering design demonstration program

317 words·~1 min read·/bill/115/s/3021/eah/section-1176

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

In this section, the term environmental impact statement means the detailed written statement required under section 102(2)(C) of the National Environmental Policy Act of 1969 ( 42 U.S.C. 4332(2)(C) ). The Secretary shall establish a demonstration program to allow a project authorized to execute pursuant to section 211 of the Water Resources Development Act of 1996 ( 33 U.S.C. 701b–13 ) (as in effect on the day before the date of enactment of the Water Resources Reform and Development Act of 2014 (128 Stat. 1193)) to begin preconstruction engineering and design on a determination by the Secretary that the project is technically feasible, economically justified, and environmentally acceptable.
For each project authorized to begin preconstruction engineering and design under subsection (b)— the project shall conform to the feasibility study and the environmental impact statement approved by the Secretary; and the Secretary and the non-Federal sponsor shall jointly agree to the construction design of the project. When reviewing the feasibility study and the environmental impact statement for a project under subsection (b), the Secretary shall follow current USACE Policy, Regulations, and Guidance, to assess potential adverse downstream impacts to the Pearl River Basin.
Upon completion of the Secretary’s determination under subsection (b), the non-Federal sponsor shall design the project in a manner that addresses any potential adverse impacts or that provides mitigation in accordance with section 906 of the Water Resources Development Act of 1986 ( 33 U.S.C. 2283 ). The authority to carry out the demonstration program under this section shall terminate on the date that is 5 years after the date of enactment of this Act. Nothing in this section supersedes, precludes, or affects any applicable requirements for a project under subsection
(b)under— section 906 of the Water Resources Development Act of 1986 ( 33 U.S.C. 2283 ); or the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 ( 42 U.S.C. 9601 et seq.).
Connectionstraces to 3
2 references not yet in our index
  • 33 USC 701b–13
  • 128 Stat. 1193
Citation graph
cites case law
Sec. 1176
Preconstruction engineering design demonstration program
Cite33 USC 701b–13
Stat.128 Stat. 1193
Cites 5Cited by 0 across 0 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.