A. For each heavy rail or commuter rail project, the licensed contractor performing the construction shall perform, with the contractor's own organization, construction work on the rail component that amounts to not less than thirty per cent of the contract price for construction of the rail component.
B. The thirty per cent self-performance requirement of subsection A of this section does not apply if the contract price for construction of the rail component is less than one-half of the total contract price for construction of the heavy rail or commuter rail project.
C. Project elements shall not be artificially added to a project to make a project into a heavy rail or commuter rail project. Project elements shall not be artificially deleted from a project to make a project not a heavy rail or commuter rail project.
D. The department may include in any heavy rail or commuter rail project:
1. Rail components.
2. Stations, maintenance or repair facilities, operations centers, office buildings or parking facilities related to heavy rail or commuter rail.
E. If any monies for a heavy rail or commuter rail project are provided by the federal government, any requirement or other provision of this section does not apply to the heavy rail or commuter rail project if the requirement or provision is in conflict with any requirement of federal law, regulation or policy, the federal government or the federal funding agency.
F. For the purposes of this section, in determining the contract price for construction of all or any part of a heavy rail or commuter rail project, the contract price for construction does not include the cost of preconstruction services or design services, as defined in section 28-7361, any other related services or the cost to procure any right-of-way or other cost of condemnation.
G. This section applies to the design-bid-build, design-build, construction-manager-at-risk and job-order-contracting project delivery methods.
H. For the purposes of this section:
1. "Heavy rail or commuter rail project" means a department facilities project for heavy rail or commuter rail, including any rail component and any stations, maintenance or repair facilities, operations centers, office buildings or parking facilities relating to heavy rail or commuter rail.
2. "Rail component" means the part of a heavy rail or commuter rail project related to the track and operation of trains on the track, including the rails, ties, track bed, subgrade, excavations, dirt, rock and other materials removal and buildup, signals and communications equipment, highway crossings and crossing gates and signals. Rail component does not include any stations, maintenance or repair facilities, operations centers, office buildings or parking facilities.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.