27-992. Mining unit or existing exploration operation

379 words·~2 min read·/az/title-27/27-992

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

A. The owner or operator of an existing exploration operation or a new or existing mining unit shall transmit a financial assurance mechanism to the state mine inspector within sixty days after a reclamation plan is approved. The inspector shall take final action on the financial assurance mechanism within thirty days after it is received.
B. In determining the amount of financial assurance to be provided for an existing exploration operation or a new or existing mining unit, the inspector shall consider the costs of approved reclamation measures stated in the reclamation plan. In computing reclamation costs, the inspector shall assume that third parties will perform the reclamation measures. The inspector shall reduce the amount of the required financial assurance to the costs of the owner or operator performing the reclamation measures if the owner or operator can demonstrate sufficient financial ability to perform the necessary reclamation or if the owner or operator meets the financial assurance reduction criteria established by rule.
Financial ability shall be established by one or more of the financial mechanisms described in 40 Code of Federal Regulations section 264.143(f).
C. Each financial assurance mechanism for an existing exploration or new or existing mining unit submitted to the inspector shall provide the amount in current dollars equal to the cost to:
1. Perform the approved reclamation measures stated in the reclamation plan on the area of surface disturbance.
2. Provide continued care and monitoring of the areas stated in the reclamation plan for revegetation for no more than three growing seasons without additional supplemental irrigation or other man-induced inputs after performing the reclamation measures unless the supplemental inputs are part of the post-mining land use. Notwithstanding this paragraph, revegetation efforts that are necessary to achieve the post-mining land use objective are considered adequate and complete if the owner or operator has taken reasonable measures to achieve vegetative success.
Technical and economic practicability as it relates to site-specific conditions and the proposed post-mining land use shall be taken into account in making that determination.
D. The inspector shall adjust the amount of financial assurance every five years or more often as necessary to adjust for new areas of planned surface disturbances or inflation or to reflect changed costs resulting from substantial modifications of the reclamation plan.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.