Sec. 42.05.767. Electric reliability organization rules; approval.
An electric reliability organization shall file with the commission each proposed rule or proposed rule change, along with an explanation of the basis and purpose of the proposed rule or proposed rule change. The commission may, on its own motion or upon complaint, propose a change to the rules of an electric reliability organization. A rule change proposed by the commission takes effect upon a finding by the commission, after notice and opportunity for public comment, that the rule change is just, reasonable, not unduly discriminatory or preferential, and in the public interest.