54-26-301. Large load contract requirements.
502 words·~2 min read·
/ut/title-54/chapter-26/54-26-301A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Effective 5/7/2025
54-26-301. Large load contract requirements.
(1)Electric service for a large-scale service request shall be provided only under one or more large load contracts with:
(a)a qualified electric utility;
(b)a large-scale generation provider; or
(c)any combination of Subsections (1)(a) and (1)(b).
(2)A large load customer shall:
(a)contract for all of the customer's projected electrical requirements under the large-scale service request; and
(b)maintain contracts with resources or load shedding capabilities sufficient to meet the customer's actual electrical requirements at all times.
(3)A large load contract with a qualified electric utility shall:
(a)ensure that all large load incremental costs are allocated to and paid by the large load customer;
(b)comply with all system requirements;
(c)require the large load customer to maintain financial security sufficient to cover the large load customer's obligations;
(d)specify:
(i)points of interconnection;
(ii)power delivery points;
(iii)the amount of electrical capacity contracted for;
(iv)the term of service; and
(v)any arrangements for backup power supply;
(e)provide curtailment provisions if the large load customer's demand exceeds the amount of contractually supported demand;
(f)identify the incremental generation resources that the qualified electric utility will use to serve the large load customer; and
(g)include provisions addressing the allocation and payment of long-term operation and maintenance costs for large load facilities.
(4)A large load contract with a large-scale generation provider that provides service through a connected electrical system shall:
(a)ensure that all large load incremental costs are allocated to and paid by the large load customer;
(b)comply with all system requirements;
(c)specify:
(i)points of interconnection;
(ii)power delivery points;
(iii)the amount of electrical capacity contracted for;
(iv)the term of service; and
(v)any arrangements for backup power supply; and
(d)provide curtailment provisions if the large load customer's demand exceeds the real-time dispatch of the large-scale generation provider's resources under the large load contract, net of transmission losses.
(5)A qualified electric utility:
(a)has no duty to serve a large load customer except as explicitly provided in a large load contract; and
(b)is not required to provide backup power to a large load customer except as explicitly provided in a large load contract.
(6)A qualified electric utility may not be required to commence design and construction of large load facilities until after:
(a)executing a large load construction contract; and
(b)obtaining commission approval in accordance with Section 54-26-302 .
(7)A qualified electric utility or large-scale generation provider shall:
(a)obtain commission approval in accordance with Section 54-26-302 before providing electric service under a large load contract; and
(b)negotiate the terms of a large load contract with a large load customer on a case-by-case basis.
(8)Within 15 business days after executing a large load contract, a person executing the contract shall submit an application for approval to the commission for review under Section 54-26-302 .
Enacted by Chapter 318 , 2025 General Session