54-23-104. Right-of-way crossing -- Construction.
102 words·~1 min read·
/ut/title-54/chapter-23/54-23-104A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Effective 5/14/2019
54-23-104. Right-of-way crossing -- Construction.
Unless the railroad notifies the fiber optic carrier in writing or electronically that the approved crossing is a serious threat to the safe operation of the railroad or to the current or future use of the railroad right-of-way, would violate any federal law or regulation applicable to a public transit district, or would violate an agreement between a public transit district and the federal government, the railroad shall issue the permit or crossing agreement and schedule flagging to occur within 45 calendar days of the approved application.
Enacted by Chapter 452 , 2019 General Session