54-17-201. Solicitation process required -- Exception.
(a)An affected electrical utility shall comply with this chapter to acquire or construct a significant energy resource after February 25, 2005.
(b)Notwithstanding Subsection (1)(a), this chapter does not apply to a significant energy resource for which the affected electrical utility has issued a solicitation before February 25, 2005.
(a)Except as provided in Subsection (3), to acquire or construct a significant energy resource, an affected electrical utility shall conduct a solicitation process that is approved by the commission.
(b)To obtain the approval of the commission of a solicitation process, the affected electrical utility shall file with the commission a request for approval that includes:
(i)a description of the solicitation process the affected electrical utility will use;
(ii)a complete proposed solicitation; and
(iii)any other information the commission requires by rule made in accordance with Title 63G, Chapter 3, Utah Administrative Rulemaking Act.
(c)In ruling on the request for approval of a solicitation process, the commission shall determine whether the solicitation process:
(i)complies with this chapter and rules made in accordance with Title 63G, Chapter 3, Utah Administrative Rulemaking Act; and
(ii)is in the public interest, taking into consideration:
(A)the dispatchability of the significant energy resource;
(B)the state's desire to have proven dispatchable generation resources operating within the state to ensure adequate resources to reliably meet the state's energy needs;
(C)whether the proposal is consistent with the state energy policy described in Section 79-6-301 ;
(D)whether it will most likely result in the acquisition, production, and delivery of electricity at the lowest reasonable cost to the retail customers of an affected electrical utility located in this state, including any lowered costs resulting from the ability to sell excess energy generated in an interstate energy market;
(E)long-term and short-term impacts;
(F)risk;
(G)reliability;
(H)financial impacts on the affected electrical utility; and
(I)other factors determined by the commission to be relevant.
(d)Before approving a solicitation process under this section the commission:
(i)may hold a public hearing; and
(ii)shall provide an opportunity for public comment.
(e)As part of the commission's review of a solicitation process, the commission may provide the affected electrical utility guidance on any additions or changes to the commission's proposed solicitation process.
(f)Unless the commission determines that additional time to analyze a solicitation process is warranted and is in the public interest, within 60 days of the day on which the affected electrical utility files a request for approval of the solicitation process, the commission shall:
(i)approve a proposed solicitation process;
(ii)suggest modifications to a proposed solicitation process; or
(iii)reject a proposed solicitation process.
(3)Notwithstanding Subsection (2), an affected electrical utility may acquire or construct a significant energy resource without conducting a solicitation process if it obtains a waiver of the solicitation requirement in accordance with Section 54-17-501 .
(4)In accordance with the commission's authority under Subsection 54-12-2 (2), the commission shall determine:
(a)whether this chapter or another competitive bidding procedure shall apply to a purchase of a significant energy resource by an affected electrical utility from a small power producer or cogenerator; and
(b)if this chapter applies as provided in Subsection (4)(a), the manner in which this chapter applies to a purchase of a significant energy resource by an affected electrical utility from a small power producer or cogenerator.
Amended by Chapter 214 , 2024 General Session
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.