38-1a-306. Substantial compliance.
(1)Substantial compliance with the requirements of this chapter is sufficient to claim, as applicable, a preconstruction lien or a construction lien.
(2)Subsection
(1)may not be construed to excuse compliance with or affect the requirement to file:
(a)a notice of preconstruction service as provided in Section 38-1a-401 in order to claim a preconstruction lien; or
(b)a preliminary notice as provided in Section 38-1a-501 in order to claim a construction lien.
Amended by Chapter 464 , 2013 General Session