11-42-302. Contracts for work in an assessment area -- Sources of payment -- Payments as work progresses.

316 words·~1 min read·/ut/title-11/chapter-42/11-42-302

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

11-42-302. Contracts for work in an assessment area -- Sources of payment -- Payments as work progresses.
(1)A contract for work in an assessment area or for the purchase of property required to make an improvement in an assessment area may require the contract obligation to be paid from proceeds from the sale of assessment bonds, interim warrants, or bond anticipation notes.
(a)To the extent that a contract is not paid from the sources stated in Subsection
(1), the local entity shall advance funds to pay the contract obligation from other legally available money, according to the requirements of the contract.
(b)A local entity may reimburse itself for an amount paid from its general fund or other funds under Subsection (2)(a) from:
(i)the proceeds from the sale of assessment bonds, interim warrants, or bond anticipation notes; or
(ii)assessments or improvement revenues that are not pledged for the payment of assessment bonds, interim warrants, or bond anticipation notes.
(c)A local entity may not reimburse itself for costs of making an improvement that are properly chargeable to the local entity or for which an assessment may not be levied.
(a)A contract for work in an assessment area may provide for payments to the contractor as the work progresses.
(b)If a contract provides for periodic payments:
(i)periodic payments may not exceed 90% of the value of the work done to the date of the payment, as determined by estimates of the project engineer; and
(ii)a final payment may be made only after the contractor has completed the work and the local entity has accepted the work.
(c)If a local entity retains money payable to a contractor as the work progresses, the local entity shall retain or withhold and release the money as provided in Section 13-8-5 .
Enacted by Chapter 329 , 2007 General Session
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.