Sec. 886. DEVELOPMENT OF PROCUREMENT ADMINISTRATIVE LEAD TIME

338 words·~2 min read·/statute-compilations/comps-13932/sec-886

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

## SEC. 886 DEVELOPMENT OF PROCUREMENT ADMINISTRATIVE LEAD TIME **[**[10 U.S.C. 2302 note](/us/usc/t10/s2302)**]** ###
(a)In General Not later than 180 days after the date of the enactment of this Act, the Secretary of Defense shall develop, make available for public comment, and finalize— ####
(1)a definition of the term “procurement administrative lead time” or “PALT”, to be applied Department of Defense-wide, that describes the amount of time from the date on which a solicitation is issued to the date of an initial award of a contract or task order of the Department of Defense; and ####
(2)a plan for measuring and publicly reporting data on PALT for Department of Defense contracts and task orders above the simplified acquisition threshold. ###
(b)Requirement for Definition Unless the Secretary determines otherwise, the amount of time in the definition of PALT developed under subsection
(a)shall— ####
(1)begin on the date on which the initial solicitation is issued for a contract or task order of the Department of Defense by the Secretary of a military department or head of a Defense Agency; and ####
(2)end on the date of the award of the contract or task order. ###
(c)Coordination In developing the definition of PALT, the Secretary shall coordinate with— ####
(1)the senior contracting official of each military department and Defense Agency to determine the variations of the definition in use across the Department of Defense and each military department and Defense Agency; and ####
(2)the Administrator of the General Services Administration on modifying the existing data system of the Federal Government to determine the date on which the initial solicitation is issued. ###
(d)Use of Existing Procurement Data Systems In developing the plan for measuring and publicly reporting data on PALT required by subsection (a), the Secretary shall, to the maximum extent practicable, rely on the information contained in the Federal procurement data system established pursuant to section 1122(a)(4) of title 41, United States Code, including any modifications to that system.
Connectionstraces to 1
Citation graph
cites case law
Sec. 886
DEVELOPMENT OF PROCUREMENT ADMINISTRATIVE LEAD TIME
Cites 1Cited by 0 across 0 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.