Tap any paragraph to write a margin note. Your notes collect in the Desk below the text and file under cases with @. The side-by-side margin rail opens on a larger screen.

Code · REGISTER · 2004-12-15 · Department of Defense (DoD) · Proposed Rules

Proposed Rules. Final rule

617 words·~3 min read·/register/2004/12/15/04-27350

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

BILLING CODE 5001-08-P DEPARTMENT OF DEFENSE 48 CFR Part 236 [DFARS Case 2003-D035] Defense Federal Acquisition Regulation Supplement; Construction and Architect-Engineer Services AGENCY: Department of Defense (DoD). ACTION: Final rule. SUMMARY: DoD has issued a final rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to update text pertaining to selection of firms for architect-engineer contracts. This rule is a result of a transformation initiative undertaken by DoD to dramatically change the purpose and content of the DFARS.
EFFECTIVE DATE: December 15, 2004. FOR FURTHER INFORMATION CONTACT: Mr. Euclides Barrera, Defense Acquisition Regulations Council, OUSD(AT&L)DPAP(DAR), IMD 3C132, 3062 Defense Pentagon, Washington, DC 20301-3062. Telephone
(703)602-0296; facsimile
(703)602-0350. Please cite DFARS Case 2003-D035. SUPPLEMENTARY INFORMATION: A. Background DFARS Transformation is a major DoD initiative to dramatically change the purpose and content of the DFARS. The objective is to improve the efficiency and effectiveness of the acquisition process, while allowing the acquisition workforce the flexibility to innovate. The transformed DFARS will contain only requirements of law, DoD-wide policies, delegations of FAR authorities, deviations from FAR requirements, and policies/procedures that have a significant effect beyond the internal operating procedures of DoD or a significant cost or administrative impact on contractors or offerors. Additional information on the DFARS Transformation initiative is available at *http://www.acq.osd.mil/dp/dars/transf.htm.* This final rule is a result of the DFARS Transformation initiative. The changes in this rule— • Revise DFARS 236.602-1 to remove procedures for establishment of evaluation criteria in the selection of firms for architect-engineer contracts. This text has been relocated to the new DFARS companion resource, Procedures, Guidance, and Information (PGI), available at *http://www.acq.osd.mil/dpap/dars/pgi.* • Remove unnecessary text on preselection boards and selection authorities at DFARS 236.602-2 and 236.602-4. • Amend DFARS 236.604 to reflect replacement of Standard Form 254, Architect—Engineer and Related Services Questionnaire, with Standard Form 330, Architect-Engineer Qualifications. DoD published a proposed rule at 69 FR 35568 on June 25, 2004. DoD received no comments on the proposed rule. Therefore, DoD has adopted the proposed rule as a final rule without change. This rule was not subject to Office of Management and Budget review under Executive Order 12866, dated September 30, 1993. B. Regulatory Flexibility Act DoD certifies that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, *et seq.* , because the changes in the rule represent no substantive change to policy with regard to selection of firms for architect-engineer contracts. C. Paperwork Reduction Act The Paperwork Reduction Act does not apply because the rule does not impose any information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501, *et seq.* List of Subjects in 48 CFR Part 236 Government procurement. Michele P. Peterson, Executive Editor, Defense Acquisition Regulations Council. Therefore, 48 CFR Part 236 is amended as follows: 1. The authority citation for 48 CFR Part 236 continues to read as follows: Authority: 41 U.S.C. 421 and 48 CFR Chapter 1. PART 236—CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS 2. Section 236.602-1 is revised to read as follows: 236.602-1 Selection criteria.
(a)Establish the evaluation criteria before making the public announcement required by FAR 5.205(c) and include the criteria and their relative order of importance in the announcement. Follow the procedures at PGI 236.602-1(a). 236.602-2 and 236.602-4 [Removed] 3. Sections 236.602-2 and 236.602-4 are removed. 4. Section 236.604 is amended by revising paragraph (c)(ii) to read as follows: 236.604 Performance evaluation.
(c)* * *
(ii)File and use the DD Form 2631, Performance Evaluation (Architect-Engineer), in a manner similar to the SF 330, Architect-Engineer Qualifications, Part II. [FR Doc. 04-27350 Filed 12-14-04; 8:45 am]
Connectionstraces to 3
2 references not yet in our index
  • 48 CFR 236
  • 41 USC 421
Citation graph
cites case law
Proposed Rules
Final rule
Cite48 CFR 236
Cite41 USC 421
Cites 5Cited by 0 across 0 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.