NRS 108.228 Notice of completion: Recording; contents; verification; delivery of copy to each prime contractor and potential lien claimant; effect of failure to deliver copy to prime contractor or lien claimant.

317 words·~1 min read·/nv/chapter-108-statutory-liens/108-228

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

NRS 108.228 Notice of completion: Recording; contents; verification; delivery of copy to each prime contractor and potential lien claimant; effect of failure to deliver copy to prime contractor or lien claimant.
1. The owner may record a notice of completion after the completion of the work of improvement.
2. The notice of completion must be recorded in the office of the county recorder of the county where the property is located and must set forth:
(a)The date of completion of the work of improvement.
(b)The owner’s name or owners’ names, as the case may be, the address of the owner or addresses of the owners, as the case may be, and the nature of the title, if any, of the person signing the notice.
(c)A description of the property sufficient for identification.
(d)The name of the prime contractor or names of the prime contractors, if any.
3. The notice must be verified by the owner or by some other person on the owner’s behalf. The notice need not be acknowledged to be recorded.
4. Upon recording the notice pursuant to this section, the owner shall, within 10 days after the notice is recorded, deliver a copy of the notice by certified mail, to:
(a)Each prime contractor with whom the owner contracted for all or part of the work of improvement.
(b)Each potential lien claimant who, before the notice was recorded pursuant to this section, either submitted a request to the owner to receive the notice or delivered a preliminary notice of right to lien pursuant to NRS 108.245 .
5. The failure of the owner to deliver a copy of the notice of completion in the time and manner provided in this section renders the notice of completion ineffective with respect to each prime contractor and lien claimant to whom a copy was required to be delivered pursuant to subsection 4.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.