85-2-231. Temporary preliminary decree, preliminary decree, and supplemental preliminary decree.

455 words·~2 min read·/mt/title-85/chapter-2/part-2/85-2-231

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

85-2-231 . Temporary preliminary decree, preliminary decree, and supplemental preliminary decree.
(1)A water judge may issue a temporary preliminary decree prior to the issuance of a preliminary decree if the temporary preliminary decree is necessary for the orderly adjudication or administration of water rights.
(a)The water judge shall issue a preliminary decree. The preliminary decree must be based on:
(i)the statements of claim before the water judge, including all claims filed pursuant to 85-2-222 for a preliminary decree issued after June 30, 2019;
(ii)the data submitted by the department;
(iii)the contents of compacts approved by the Montana legislature and the tribe or federal agency or, lacking an approved compact, the filings for federal and Indian reserved rights; and
(iv)any additional data obtained by the water judge.
(b)The preliminary decree must be issued within 90 days after the close of the special filing period set out in 85-2-702
(3)or as soon after the close of that period as is reasonably feasible.
(c)In a basin in which a water judge has issued a preliminary decree prior to July 1, 2019, the water judge shall issue a supplemental preliminary decree that includes but is not limited to claims for exempt rights, as defined in 85-2-222 , that were not included in a preliminary decree and for which notice has not been provided under 85-2-233(6).
(d)The water judge may issue an interlocutory decree if an interlocutory decree is otherwise necessary for the orderly administration of water rights.
(3)A temporary preliminary decree may be issued for any hydrologically interrelated portion of a water division, including but not limited to a basin, subbasin, drainage, subdrainage, stream, or single source of supply of water, or any claim or group of claims at a time different from the issuance of other temporary preliminary decrees.
(4)The temporary preliminary decree, preliminary decree, or supplemental preliminary decree must contain the information and make the determinations, findings, and conclusions required for the final decree under 85-2-234 .
(5)If the water judge is satisfied that the report of the water master meets the requirements for the preliminary decree and is satisfied with the conclusions contained in the report, the water judge shall adopt the report as the preliminary decree. If the water judge is not satisfied, the water judge may recommit the report to the master with instructions or modify the report and issue the preliminary decree.
(6)The department shall examine claims in basins that were verified rather than examined as ordered by the water court. The objection and hearing provisions of Title 85, chapter 2, part 2, apply to these claims. (Subsection
(6)terminates June 30, 2028--sec. 10, Ch. 269, L. 2015.)
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.