§12–532.
(a)Except as provided in subsection
(c)of this section, Cecil County shall obtain the following by competitively bid contract awarded to the lowest responsive and responsible bidder:
(1)the building or repair of a road; and
(2)the purchase or lease of road or construction equipment or machinery.
(1)The governing body of Cecil County shall advertise for bids on a contract under subsection
(a)of this section in at least one newspaper of general circulation in the county.
(2)The advertisement shall:
(i)appear at least once;
(ii)appear at least 1 week, but not more than 30 days, before the final date for submitting bids;
(iii)if the contract relates to building or repairing a road, set forth the place where the road is to be built or repaired;
(iv)include a description of the goods or services required under the contract;
(v)state that sealed bids for goods or services will be received until the date designated in the advertisement; and
(vi)designate a date for the opening of the bids.
(1)Subsections
(a)and
(b)of this section do not apply to an expenditure that:
(i)is $10,000 or less; or
(ii)the governing body of Cecil County by a recorded majority vote taken at a public meeting declares to be an emergency expenditure.
(2)For an expenditure under this subsection, the governing body may determine:
(i)the manner of providing for the expenditure; and
(ii)if the building or repair is by contract, the manner in which the contract is awarded.
(1)A contract entered into in violation of subsection
(a)or
(b)of this section is void, unless:
(i)a court determines in a judicial action that all parties acted in good faith; and
(ii)the parties have substantially complied with the provisions of subsections
(a)and
(b)of this section.
(2)If a contract is void under this subsection, the governing body of Cecil County shall compensate the contractor for costs actually incurred if the contractor:
(i)acted in good faith;
(ii)did not directly contribute to the violation; and
(iii)did not know of the violation.
(e)A person who willfully violates this section is guilty of a misdemeanor and on conviction is subject to a fine not exceeding $1,000.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.