Sec. 6001. Authorization of final feasibility studies
593 words·~3 min read·
/bill/114/s/2848/is/section-6001A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
The following final feasibility studies for water resources development and conservation and other purposes are authorized to be carried out by the Secretary substantially in accordance with the plan, and subject to the conditions, described in the respective reports designated in this section: A. State B. Name C. Date of Report of Chief of Engineers D. Estimated Costs 1. TX Brazos Island Harbor November 3, 2014 Federal: $116,116,000 Non-Federal: $135,836,000 Total: $251,952,000 2.
LA Calcasieu Lock December 2, 2014 Federal: $16,700,000 Non-Federal: $0 Total: $16,700,000 3. NH, ME Portsmouth Harbor and Piscataqua River February 8, 2015 Federal: $15,580,000 Non-Federal: $5,190,000 Total: $20,770,000 4. KY Green River Locks and Dams 3, 4, 5, and 6 and Barren River Lock and Dam 1 Disposition April 30, 2015 Federal: $0 Non-Federal: $0 Total: $0 5. FL Port Everglades June 25, 2015 Federal: $220,200,000 Non-Federal: $102,500,000 Total: $322,700,000 6. AK Little Diomede August 10, 2015 Federal: $26,015,000 Non-Federal: $2,945,000 Total: $28,960,000 7.
SC Charleston Harbor September 8, 2015 Federal: $224,300,000 Non-Federal: $269,000,000 Total: $493,300,000 8. AK Craig Harbor March 16, 2016 Federal: $29,062,000 Non-Federal: $3,255,000 Total: $32,317,000. A. State B. Name C. Date of Report of Chief of Engineers D. Estimated Costs 1. TX Leon Creek Watershed, San Antonio June 30, 2014 Federal: $18,314,000 Non-Federal: $9,861,000 Total: $28,175,000 2. MO, KS Armourdale and Central Industrial District Levee Units, Missouri River and Tributaries at Kansas City January 27, 2015 Federal: $207,036,000 Non-Federal: $111,481,000 Total: $318,517,000 3.
KS City of Manhattan April 30, 2015 Federal: $15,440,100 Non-Federal: $8,313,900 Total: $23,754,000 4. KS Upper Turkey Creek Basin December 22, 2015 Federal: $24,584,000 Non-Federal: $13,238,000 Total: $37,822,000 5. NC Princeville February 23, 2016 Federal: $14,001,000 Non-Federal: $7,539,000 Total: $21,540,000. A. State B. Name C. Date of Report of Chief of Engineers D. Estimated Initial Costs and Estimated Renourishment Costs 1. SC Edisto Beach, Colleton County September 5, 2014 Initial Federal: $13,733,850 Initial Non-Federal: $7,395,150 Initial Total: $21,129,000 Renourishment Federal: $16,371,000 Renourishment Non-Federal: $16,371,000 Renourishment Total: $32,742,000 2.
FL Flagler County December 23, 2014 Initial Federal: $9,218,300 Initial Non-Federal: $4,963,700 Initial Total: $14,182,000 Renourishment Federal: $15,390,000 Renourishment Non-Federal: $15,390,000 Renourishment Total: $30,780,000 3. NC Bogue Banks, Carteret County December 23, 2014 Initial Federal: $24,263,000 Initial Non-Federal: $13,064,000 Initial Total: $37,327,000 Renourishment Federal: $114,728,000 Renourishment Non-Federal: $114,728,000 Renourishment Total: $229,456,000 4.
NJ Hereford Inlet to Cape May Inlet, New Jersey Shoreline Protection Project, Cape May County January 23, 2015 Initial Federal: $14,040,000 Initial Non-Federal: $7,560,000 Initial Total: $21,600,000 Renourishment Federal: $41,215,000 Renourishment Non-Federal: $41,215,000 Renourishment Total: $82,430,000 5. LA West Shore Lake Pontchartrain June 12, 2015 Federal: $466,760,000 Non-Federal: $251,330,000 Total: $718,090,000 6. CA Encinitas-Solana Beach Coastal Storm Damage Reduction March 29, 2016 Initial Federal: $20,166,000 Initial Non-Federal: $10,858,000 Initial Total: $31,024,000 Renourishment Federal: $68,125,000 Renourishment Non-Federal: $68,125,000 Renourishment Total: $136,430,000.
A. State B. Name C. Date of Report of Chief of Engineers D. Estimated Costs 1. IL, WI Upper Des Plaines River and Tributaries June 8, 2015 Federal: $199,393,000 Non-Federal: $107,694,000 Total: $307,087,000 2. CA South San Francisco Bay Shoreline December 18, 2015 Federal: $69,521,000 Non-Federal: $104,379,000 Total: $173,900,000. A. State B. Name C. Date of Report of Chief of Engineers D. Estimated Costs 1. FL Central Everglades Planning Project, Comprehensive Everglades Restoration Plan, Central and Southern Florida Project December 23, 2014 Federal: $976,375,000 Non-Federal: $974,625,000 Total: $1,951,000,000 2.
OR Lower Willamette River Environmental Dredging December 14, 2015 Federal: $19,143,000 Non-Federal: $10,631,000 Total: $29,774,000 3. WA Skokomish River December 14, 2015 Federal: $12,782,000 Non-Federal: $6,882,000 Total: $19,664,000 4. CA LA River Ecosystem Restoration December 18, 2015 Federal: $375,773,000 Non-Federal: $980,835,000 Total: $1,356,608,000.