Sec. 02.15.104. Relocation of utility facilities incident to airport projects.

320 words·~1 min read·/ak/title-2/chapter-15/02-15-104

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

Sec. 02.15.104. Relocation of utility facilities incident to airport projects.
(a)If, incident to the construction of an airport project, the department determines and orders that a utility facility located across, along, over, under, or within a state airport must be changed, relocated, or removed, the utility owning or maintaining the facility shall change, relocate, or remove it in accordance with the order, within a reasonable time set by the department in the order.
(b)If the utility facility is not changed, relocated, or removed in accordance with the order, a permit authorizing the facility issued by the department under AS 02.15.102 becomes invalid and the facility will be considered an unauthorized encroachment subject to the provisions of AS 02.15.114 .
(c)The cost of change, relocation, or removal, as defined in AS 02.15.260 , ordered under
(a)of this section is to be paid as follows:
(1)by the department as a cost of airport construction, if the utility facility is installed or authorized after June 11, 1986 under a utility permit or a regulation and is installed in the location specified in the permit;
(2)by the department as a cost of airport construction, if the facility was installed before June 11, 1986 under a utility permit or utility easement and is in the location specified in the permit or easement;
(3)by the department as a cost of airport construction, if the utility facility was installed before the location became part of a state airport or before permits were required;
(4)by the department as a cost of airport construction, if the utility permit that requires the utility to pay the relocation cost was issued more than five years before the contract for the airport construction project was first advertised;
(5)by the utility in all other cases unless the commissioner finds it is in the public interest for the cost to be paid by the department.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.